Programme, progress and results

Programme Freshman-project

  • 2020 Q1: preparation and execution of pilot drilling
  • 2020 Q2:
    • monitoring water quality test drilling
    • effects studies groundwater and nature
  • 2020, 1 July: Official start Freshman
  • 2020 Q3 + Q4:
    • application permits for the pilot and replication
    • final design field of wells and purification
    • Tendering field of wells and purification
  • 2021 Q1: realization of the field of wells and purification
  • 2021 Q2: test phase
  • 2021 Q3 - 2023 Q3: extraction and purification of brackish groundwater
  • 2022 Q1: start replication project in Avekapelle
  • 2023 Q4:
    • start experiments on capacity bridging
    • end replication project Avekapelle
  • 2025 Q1-Q2: finalization of project and final reporting

Progress

The design

The design of the installations (field of wells and purification) is ready. Two wells are provided and six monitoring wells at a distance of 5 to 120 meters from the extraction wells. In addition, an innovative measurement method (cross hole ERT) is planned in a 10 x 10 meter quadrant around the extraction wells, with which the effect of extraction on the sweet-salt distribution in the subsurface can be imaged in a three-dimensional way. The extraction will produce about 50 m3/hour of brackish water, of which 12 m3/hour will be desalinated. The excess brackish water, together with the residual product of the desalination (concentrate), will be discharged into the sewer. Agreements have been made with the sewer manager (Municipality of The Hague) and the relevant water board (HH Delfland).

The permits

Permits have been requested for the construction of the installations (environmental permit), for the pumping of brackish groundwater (Water Act) and for the discharge of the excess brackish water and concentrate on the sewer (ongoing). For the permit applications, studies have been carried out on the impact of the pilot on the environment (geohydrological and ecological); these impacts were minimal and are not a limitation for starting the pilot. The only remaining concern is nitrogen emissions during the construction of the well field; we are in discussions with the licensee about this.

Drilling

In support of the exploratory studies on the impact of the pilot on the environment, a pilot drilling has been carried out at the pilot site, which characterizes the soil composition and the sweet-salt distribution in the subsurface (up to 200 meters deep!). The result of this test drilling is in the figure below. Three different types of water can be distinguished. Up to a depth of 80 meters, the groundwater is sweet; then it goes through brackish (80-110 meters) to salt (deeper than 110 meters).

Understanding and modeling

In the pilot we will gain operational experience with extraction and purification (desalination by reverse osmosis) of brackish groundwater, and with extraction and control in a varying brackish/sweet groundwater environment. In this way, we gain a better understanding of the operation of the fresh/salt groundwater system on site, so that we can also better understand and model the larger concept of brackish water extraction. This is essential to know whether brackish water could also be extracted more widely in dunes and other coastal zones.

Tabel brak grondwater